Residents on Two Rivers’ north side could see brief interruptions in water pressure this week.
The city is starting to drain the north-side reservoir, requiring it to be taken offline.
The 2-million-gallon reservoir will be inspected, cleaned, chlorinated, and returned to service.
The entire process will take about 10 days and may cause a slight reduction in water pressure for north side residents.
The reservoir is expected to be back to normal on June 5th.
Two Rivers crews will also address existing issues related to the current overflow pipe configuration.
The correction will be fixed by installing a new overflow pipe on the west side of the reservoir.