Major work on Interstate 43 will continue this week in Sheboygan County.
The Wisconsin Department of Transportation explains that it will continue rehabilitation work on various structures on 43 between State Highway 28 and County Road V, including the County Road PP overpass.
Along with that work will be closures this week, including at WIS 28.
The north and southbound ramps to Highway 28 will be closed nightly, from 8:00 p.m. to 6:00 a.m. beginning Wednesday (August 12th) and ending Friday (August 14th).
Likewise, the north and southbound ramps on I-43 to State Highway 23 will be closed daily between 8:00 p.m. and 6:00 a.m. as well.
Additional work on 43 in Sheboygan County this week is set to include milling and paving operations along the entire project length, as well as sign work along westbound WIS 23 from County Road Y to Taylor Drive.
More information on the I-43 rehabilitation project in the Sheboygan area can be found by visiting projects.511wi.gov.